Project Features
Completion: 1996
It is located at Walt Disney World in Orlando, Florida. The Canam plant in Jacksonville, Florida and its erection team respectively fabricated and assembled in 80 days 2,100 tons of structural steel and 185 tons of joists totaling more than 10,000 steel members. Among these were 28 trusses measuring 165 feet in length and weighing up to 44 tons each. These trusses were shipped in three pieces after being fully shop assembled.
Through its vast capabilities, Canam was able to complete steel fabrication and erection six weeks ahead of schedule.
- Owner: Disney Development Corporation
- Contractor: Centex Rooney Construction Company
- Engineer: Haynes, Whaley & Associates, Inc.
- Architect: Glover, Smith & Bode, Inc.
- Tonnage: 2,285 tons
|